Anticipated events leading up to Reaffirmation of Accreditation in June 2014
| Year |
Month |
Broward Action |
Primary Responsibility |
SACS-COC Action |
| 2011 |
February |
Appoint Steering Committee |
President/Provost |
|
| |
September |
Create Sub-Committees |
Steering Committee |
|
| |
October |
Develop QEP Topic Identification Process |
QEP Committee |
|
| |
| 2012 |
January |
Identify QEP Chair |
Provost |
|
| |
January - May |
Begin first draft of Compliance Certification |
Sub-Committees |
|
| |
June - August |
Further document Compliance |
Sub-Committees |
|
| |
August 3 |
Deadline for 3 QEP Proposal Submissions |
Writing Groups |
|
| |
September |
Employ editor for Compliance Cert. and QEP |
Provost |
|
| |
September 25 |
BOT Reviews QEP Topic |
BOT |
|
| |
October |
Create Hospitality Committee |
Provost |
|
| |
October-December |
Refine and Expand QEP |
QEP Committee |
|
| |
December 19 |
First Draft of Compliance Certification Ready |
Steering Committee |
|
| |
| 2013 |
February 18 |
Host SACS-COC VP Mark Smith |
President |
|
| |
February - March 14 |
Finalize Compliance Certification |
|
|
| |
March 14 |
Submit Compliance Certification |
SACS Liaison |
|
| |
May 8 |
Off-site Committee Reviews Compliance Certification |
|
Off-Site Review |
| |
June |
Receive Off-site Report |
President |
|
| |
June - August |
Prepare Focused Report Finalize QEP Proposal |
Steering Committee |
|
| |
August 15 |
Submit QEP and Focused Report (4-6 weeks prior to On-Site visit) |
SACS-COC Liaison |
|
| |
October 8-10 |
Host On-Site Committee |
Hospitality Committee |
On-Site Visit |
|
November |
Receive Report of On-Site Committee |
President |
|
| |
November-December |
Prepare Response to Committee Report |
Steering Committee |
|
| |
| 2014 |
January - March |
Prepare Response to Committee Report |
Steering Committee |
|
| |
March 10 |
Submit Response to Committee Report |
SACS-COC Liaison |
|